ESC

Click the "allow" button if you want to receive important news and updates from immigrationboards.com


Immigrationboards.com: Immigration, work visa and work permit discussion board

Welcome to immigrationboards.com!

Login Register Do not show

Start date delay after CoS assigned and applied for visa

Only for the UK Skilled Worker visas, formerly known as Tier 2 visa route

Moderators: Casa, archigabe, CR001, push, JAJ, ca.funke, Amber, zimba, vinny, Obie, EUsmileWEallsmile, batleykhan, meself2, geriatrix, John, ChetanOjha

Locked
simbha
Newly Registered
Posts: 2
Joined: Fri Apr 08, 2022 9:12 pm
India

Start date delay after CoS assigned and applied for visa

Post by simbha » Fri Apr 08, 2022 9:49 pm

Hi,

I just got a job in the UK and got my CoS assigned. The start and end dates are as follows

CoS Start: April 6,2022
CoS End: July 6, 2022
Work start date: Jun 6, 2022

I am in the process of applying for visa. I am reading online that with the Ukraine situation visa processing might be delayed. I have a few basic questions and hope someone can help me out

1. If my visa is delayed and I cannot get it before Jun 6, can the company amend the start date to a new date on the existing CoS?

2. If option 1 is not possible and if a new CoS is needed, can I used the visa that is issued along with new CoS to enter UK and begin work?

3. If option 2 is also not possible, do I need a new CoS and new visa? If so I might continue to have the same issues since visa processing timeline is out of our hand.

Thanks

ywlgy
Senior Member
Posts: 650
Joined: Mon May 03, 2021 5:05 pm
United Kingdom

Re: Start date delay after CoS assigned and applied for visa

Post by ywlgy » Fri Apr 08, 2022 11:30 pm

1. Your company can add a sponsor note to the existing CoS if there is delay.
DISCLAIMER: Advice given is based on my past experience and/or my interpretation of Immigration Rules and UKVI documents.

simbha
Newly Registered
Posts: 2
Joined: Fri Apr 08, 2022 9:12 pm
India

Re: Start date delay after CoS assigned and applied for visa

Post by simbha » Sat Apr 09, 2022 12:32 pm

Thank you very much. That is very helpful. I have another question. Is it possible to also change the start date in the CoS after the visa is issued in case I can’t wrap up personal things before start date?
Thanks

ywlgy
Senior Member
Posts: 650
Joined: Mon May 03, 2021 5:05 pm
United Kingdom

Re: Start date delay after CoS assigned and applied for visa

Post by ywlgy » Sat Apr 09, 2022 5:33 pm

No, it cannot be changed after issuance.
You must normally stop sponsoring the worker and inform us via your SMS
account if the start date is delayed by more than 28 days after whichever is
the latest of:
• the start date recorded on the worker’s CoS (including any amendment to
that date you have told us about via SMS while the worker was awaiting a
decision on their application)
• the date the worker’s entry clearance (visa) becomes valid
• the date the worker is granted permission to enter or permission to stay