ESC

Click the "allow" button if you want to receive important news and updates from immigrationboards.com


Immigrationboards.com: Immigration, work visa and work permit discussion board

Welcome to immigrationboards.com!

Login Register Do not show

Out-of-country skilled worker visa application timelines

Only for the UK Skilled Worker visas, formerly known as Tier 2 visa route

Moderators: Casa, push, JAJ, ca.funke, Amber, zimba, vinny, Obie, EUsmileWEallsmile, batleykhan, meself2, geriatrix, John, ChetanOjha, archigabe

Post Reply
geriatrix
Moderator
Posts: 24755
Joined: Fri Mar 17, 2006 3:30 pm
Location: does it matter?

Out-of-country skilled worker visa application timelines

Post by geriatrix » Thu Jul 22, 2010 12:29 pm

Please do not post in this thread if you have made an application from within the UK.

Interested members can post their application processing timelines here for the benefit of others. This will help members to view the timelines at one place rather than posting the same rhetorical questions time and again (e.g.- Can some please tell me processing times for ABC country or city / when will my application be decided / how long do I need to wait etc. etc.) and will help reduce clutter on the database too, so you will be doing a good cause.

Please do not forget to include the following details in your post:
1. Category applying under (General / ICT / other)
2. Country of application
3. City of Visa Application Centre
4. Date of application
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from
7. Duration for Entry Clearance
8. Date passport received

Tip: Ideally timelines should be posted only after a decision is received but if writing initial post before a decision / passport is received (i.e.- giving details of points 1 to 5 only), please make an effort to edit the original post when coming back to provide update (providing inputs to points 6 to 8 ). This will help members looking for approx. timeslines to figure out end-to-end processing time of a given application(s) at one place itself.

Also, please refrain from chattering in this topic. To keep it high-value, please just read it and only post when you have something of substance to contribute (timelines only). All off-topic posts and posts enquiring about current timelines will be deleted without notice.


We thank you for your understanding.




regards

ramesh135
Newly Registered
Posts: 8
Joined: Thu Jul 15, 2010 11:05 am

Post by ramesh135 » Mon Jul 26, 2010 7:26 pm

1. Category applying under (General / ICT / other) - Tier 2 Sponsored
2. Country of application - India
3. City of Visa Application Centre - Bangalore India
4. Date of application - 15July2010
5. Date of submission of documents - 15July2010
6. Date Entry Clearance valid from - 22July2010
7. Duration for Entry Clearance - 2 years
8. Date passport received - 23July2010

sriaravindan
Newly Registered
Posts: 6
Joined: Wed Jul 21, 2010 2:49 pm
Location: Bangalore

Post by sriaravindan » Thu Jul 29, 2010 11:49 pm

1. Category applying under (General / ICT / other): ICT
2. Country of application: India
3. City of Visa Application Centre: Bangalore VFS
4. Date of application:12 july 2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from:23 july
7. Duration for Entry Clearance:13 months
8. PP recieved: 29 July 2010

mkh
Junior Member
Posts: 76
Joined: Thu Jul 01, 2010 5:30 am

Post by mkh » Wed Aug 11, 2010 9:40 am

1. Category applying under (General / ICT / other) - Tier 2 General
2. Country of application - Bangladesh
3. City of Visa Application Centre - Dhaka
4. Date of application - 23May2010
5. Date of submission of documents - 23May2010
6. Date Entry Clearance valid from - 10August2010
7. Duration for Entry Clearance - 3 years
8. Date passport received - 11August2010

h_a
Junior Member
Posts: 50
Joined: Mon Jun 28, 2010 11:05 am

Post by h_a » Mon Aug 16, 2010 12:01 pm

1. Category applying under (General / ICT / other): TIER 2 GENERAL
2. Country of application: PAKISTAN
3. City of Visa Application Centre: KARACHI
4. Date of application: 25TH MAY 2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from: 3-08-2010
7. Duration for Entry Clearance: 1 YEAR
8. Date passport received : 16TH AUG 2010

Gerel
Newly Registered
Posts: 7
Joined: Tue Nov 10, 2009 1:43 pm
Location: London

Waiting over three months

Post by Gerel » Wed Sep 15, 2010 11:40 am

1. Category applying under- General
2. Country of application - Mongolia
3. City of Visa Application Centre - Beijing
4. Date of application - 14.06.10
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from - none
7. Duration for Entry Clearance - none
8. Date passport received - not received yet

I'm basically waiting for my Tier2 Generel for nearly four months and I still haven't received an answer as to why.

indiansemail
Newly Registered
Posts: 23
Joined: Fri Oct 15, 2010 4:44 pm
Location: UK

Post by indiansemail » Wed Nov 24, 2010 7:31 pm

1. Category applying under (General / ICT / other): TIER 2 ICT
2. Country of application: India
3. City of Visa Application Centre: Mumbai North
4. Date of application: 15 Nov 2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from: 22-11-2010
7. Duration for Entry Clearance: 1 YEAR
8. Date passport received : 24TH Nov 2010

3000rpm
Newly Registered
Posts: 16
Joined: Thu Oct 14, 2010 5:47 pm

Post by 3000rpm » Fri Jan 14, 2011 9:10 pm

1. Category applying under (General / ICT / other) - Tier 2 Sponsored
2. Country of application - Indonesia
3. City of Visa Application Centre - Jakarta Indonesia
4. Date of application - 10 January 2011
5. Date of submission of documents - 10 January 2011
6. Date Entry Clearance valid from - 13 January 2011
7. Duration for Entry Clearance - 3 years
8. Date passport received - 13 January 2011

baba79
Newly Registered
Posts: 4
Joined: Sat Oct 16, 2010 7:07 am

Post by baba79 » Thu Jan 20, 2011 1:25 pm

1. Category applying under (General / ICT / other) : Tier 2 Dependent
2. Country of application : India
3. City of Visa Application Centre : Bangalore
4. Date of application : 15th December 2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from : 10th Jan 2011
7. Duration for Entry Clearance : 20 months
8. Date passport received : 14th Jan 2011

neerajbans
Newly Registered
Posts: 3
Joined: Mon Jan 31, 2011 11:55 pm
Location: London

UK Tier

Post by neerajbans » Mon Jan 31, 2011 11:57 pm

Category applying under (General / ICT / other) : Tier 2 Dependent
2. Country of application : India
3. City of Visa Application Centre : Mumbai North
4. Date of application : 6th January 2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from : 28th Jan 2011
7. Duration for Entry Clearance : 20 months
8. Date passport received : 1st Feb 2011

midpisces
Newly Registered
Posts: 12
Joined: Mon Jan 31, 2011 6:13 pm

Post by midpisces » Wed Feb 02, 2011 3:19 pm

1. Category applying under (General / ICT / other)
2. Country of application - Pakistan
3. City of Visa Application Centre - Lahore
4. Date of application - 20/12/2010
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from - 13/01/2011
7. Duration for Entry Clearance - 7 months & 20 days
8. Date passport received - 27/01/2011

User avatar
mjcr28
Member
Posts: 107
Joined: Fri Jan 28, 2011 7:12 pm
Location: London
Mood:
India

Post by mjcr28 » Thu Feb 03, 2011 9:45 am

1. Category applying under- T2 General
2. Country of application - INDIA
3. City of Visa Application Centre - VFS MUMBAI NORTH
4. Date of application - 25.10.10
5. Date of submission of documents (same as above).
6. Date Entry Clearance valid from - none
7. Duration for Entry Clearance - none
8. Date passport received - not received yet

niffer
Newly Registered
Posts: 3
Joined: Fri Feb 11, 2011 1:13 pm

Post by niffer » Fri Mar 04, 2011 11:42 am

1. Category applying under (General / ICT / other) - General
2. Country of application - Australia
3. City of Visa Application Centre - Canberra
4. Date of application - 21 February 2011
5. Date of submission of documents (if different from 3 above). n/a
6. Date Entry Clearance valid from - 4 March 2011
7. Duration for Entry Clearance - 2 years
8. Date passport received - 8 March 2011

toshu20
Newly Registered
Posts: 7
Joined: Mon Feb 21, 2011 1:06 pm

Post by toshu20 » Thu Mar 31, 2011 1:21 pm

1. Category applying under (General / ICT / other) - Tier 2 ICT Dependent
2. Country of application - India
3. City of Visa Application Centre - VFS, New Delhi, India
4. Date of application - 21-Mar-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from 30-Mar-2011
7. Duration for Entry Clearance - Same as Main applicant
8. Date passport received - 31-Mar-2011

isha123
Newly Registered
Posts: 27
Joined: Thu Apr 21, 2011 4:35 am
Location: India

Tier 2 ICT Dependent Visa for Baby

Post by isha123 » Thu May 05, 2011 3:20 pm

1. Category applying under (General / ICT / other) - Tier 2 ICT Dependent (baby)
2. Country of application - India
3. City of Visa Application Centre - VFS, New Delhi, India
4. Date of application - 13-Apr-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from 12-May-2011
7. Duration for Entry Clearance - Same as mine
8. Date passport received - 13-May-2011
Last edited by isha123 on Fri May 13, 2011 2:08 pm, edited 1 time in total.

mayankpant
Newly Registered
Posts: 16
Joined: Tue May 10, 2011 3:25 am

Post by mayankpant » Tue May 10, 2011 3:35 am

1. Category applying under (General / ICT / other) - Tier 2 ICT
2. Country of application - India
3. City of Visa Application Centre - VFS, Bangalore, India
4. Date of application - 20-Apr-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from Waiting
7. Duration for Entry Clearance - Waiting
8. Date passport received - Waiting

gulkan
Newly Registered
Posts: 4
Joined: Tue May 10, 2011 4:27 am

Post by gulkan » Tue May 10, 2011 4:31 am

1. Category applying under (General / ICT / other) - Tier 2 ICT
2. Country of application - India
3. City of Visa Application Centre - VFS, Bangalore, India
4. Date of application - 21-Apr-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from Waiting
7. Duration for Entry Clearance - Waiting
8. Date passport received - Waiting

mkh
Junior Member
Posts: 76
Joined: Thu Jul 01, 2010 5:30 am

Post by mkh » Wed May 11, 2011 12:23 pm

My wife and son applied for tier 2 dependent visa
1. Category applying under (General / ICT / other) - Tier 2 dependent
2. Country of application - Bangladesh
3. City of Visa Application Centre - Dhaka
4. Date of application - 18April2011
5. Date of submission of documents - 18April2011
6. Date Entry Clearance valid from - 10May2011
7. Duration for Entry Clearance - 3 years
8. Date passport received - 11May2011

yeeha
Newly Registered
Posts: 17
Joined: Fri Jan 07, 2011 12:27 pm

Post by yeeha » Thu May 12, 2011 7:43 am

1. Category applying under- T2 General
2. Country of application - MALAYSIA
3. City of Visa Application Centre - VFS KUALA LUMPUR
4. Date of application - 05.05.11
5. Date of submission of documents (same as above).
6. Date Entry Clearance valid from - 16.05.11
7. Duration for Entry Clearance - 16.06.14
8. Date passport received - 12.05.11

garora8
- thin ice -
Posts: 19
Joined: Tue Mar 29, 2011 11:13 pm

Post by garora8 » Thu May 12, 2011 11:37 am

1. Category applying under Tier 2 Depandants
2. Country of application - India
3. City of Visa Application Centre - Delhi India
4. Date of application - 11April 2011
5. Date of submission of documents - 11April 2011
6. Date passport received - 12May2011

teh_pwnerer
Newly Registered
Posts: 1
Joined: Sat May 14, 2011 7:20 am

Post by teh_pwnerer » Sat May 14, 2011 7:22 am

1. Category applying under (General / ICT / other) - Tier 2 ICT
2. Country of application - India
3. City of Visa Application Centre - VFS, Mumbai (south), India
4. Date of application - 21-Apr-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from 16-May-2011
7. Duration for Entry Clearance - 7 months
8. Date passport received - 16-May-2011

puneetbobra
Newly Registered
Posts: 1
Joined: Fri May 20, 2011 11:06 am
Location: London

Tier 2 ITC Dependent Visa

Post by puneetbobra » Fri May 20, 2011 11:13 am

1. Category applying under (General / ICT / other) - Tier 2 ICT (Dependant)
2. Country of application - India
3. City of Visa Application Centre - VFS, Mumbai (North), India
4. Date of application - 26-Apr-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from: 27-May-2011
7. Duration for Entry Clearance - 8 monthns
8. Date passport received - 30-May-2011

dolfintown
Newly Registered
Posts: 6
Joined: Wed Jun 01, 2011 1:05 pm
India

Tier 2 General (Dependant)

Post by dolfintown » Wed Jun 01, 2011 1:08 pm

1. Category applying under (General / ICT / other) - Tier 2 General (Dependant)
2. Country of application - India
3. City of Visa Application Centre - VFS, Hyderabad, India
4. Date of application - 24-May-2011
5. Date of submission of documents (if different from 3 above). - Same as above
6. Date Entry Clearance valid from: 07/06/2011
7. Duration for Entry Clearance - same as me
8. Date passport received - 10/06/2011
Last edited by dolfintown on Fri Jun 10, 2011 9:59 pm, edited 3 times in total.

nvenon
Newly Registered
Posts: 6
Joined: Wed May 11, 2011 10:44 am

Post by nvenon » Sun Jun 05, 2011 7:01 am

1. Category applying under (General / ICT / other) : General
2. Country of application : India
3. City of Visa Application Centre : Chennai
4. Date of application : 19/05/2011
5. Date of submission of documents (if different from 3 above).
6. Date Entry Clearance valid from : 17/06/2011
7. Duration for Entry Clearance : 17/06/2011 to 29/07/2014
8. Date passport received : 04/06/2011

cloudnumbernine4u
Newly Registered
Posts: 2
Joined: Mon Apr 18, 2011 6:34 pm

Out of Country Tier 2 General Application timeline

Post by cloudnumbernine4u » Sun Jun 19, 2011 9:42 pm

1. Category applying under (General / ICT / other) : Tier 2 General (self and spouse' dependant both together)
2. Country of application : India
3. City of Visa Application Centre : Mumbai South
4. Date of application : 09/05/2011
5. Date of submission of documents : 09/05/2011
6. Date Entry Clearance valid from : 23/05/2011
7. Duration for Entry Clearance : 23/05/2011 to 22/06/2014
8. Date passport received : 23/05/2011

Post Reply